Where a Court makes an order for specific performance a
party to a contract is compelled to carry out his contractual obligations. This
remedy was created in order to provide relief where damages may not be
appropriate.
It is based on the principle that a person should be
entitled to have that which he has contracted for. An essential prerequisite is
a valid enforceable contract. The terms of this contract must also be
sufficiently certain and the onus lies upon the plaintiff to prove this.
Specific performance will not be granted where there is an adequate common law
remedy
In Wilson v
Northampton and Banbury Junction Railway Co it was stated that the court
gives specific performance instead of specific performance only when it can by
that means do more perfect and complete justice.
The appropriateness of specific performance is very much
dependant on the type of contract in question. For example, a contract for the
sale of land could fall under the remit of specific performance while contracts
which require a large amount of supervision generally do not, as the courts are
aware that in such cases, specific performance may be akin to slavery.
Like all equitable remedies, specific performance is
discretionary in nature. In Conlon v Murray it was stated that this
discretion is not arbitrary, but is to be exercised on the principles which
have been worked out in a multitude of decided cases.
In O’Neill v Ryan it
was stated that there may well be cases where the courts decide it is not fair
to specifically perform the contract, and so they will grant damages instead.
An order for specific performance is often sought in
relation to contracts for the sale of land. While it cannot be said that a
plaintiff is entitled to a decree in these circumstances, in practice an order
will usually be granted provided that a valid contract exists and the onus lies
upon the defendant to establish why the remedy should be refused. This is
because land is unique and so will not allow for the plaintiff to be easily
compensated via damages.
It is important to note that to successfully seek an order
of specific performance of a contract for the sale of land it is necessary to
comply with certain requirements. First, there must be a valid contract made
for consideration. Once this is established there must be compliance with the
requirement that there is a written accord of the transaction, or there must be
some good reason why equity will not insist on compliance.
In Jodifern Ltd v
Fitzgerald it was stated that in a
claim for specific performance a plaintiff must establish the making of an
enforceable concluded agreement. Where the agreement is a verbal one, the
plaintiff must establish not only the concluded agreement but also the
existence of a note or a memorandum signed by the defendant.
In Lynch v O’Meara it
was made clear that if the negotiations between the parties have not culminated
in a contract the plaintiff’s claim for specific performance will fail.
Uncertainty has surrounded the issue of whether certain matters, for example
the payment of a deposit must be addressed in order for there to be a concluded
and complete agreement.
Uncertainty has surrounded the issue of whether certain
matters, for example the payment of a deposit, must be addressed in order for
there to be a concluded agreement. In Boyle
v Lee it was stated that the amount of the deposit to be made is a very
important issue and so must be part of the concluded agreement, unless it was
agreed that no deposit would be made.
However, in Supermacs
Ireland v Katesan Justice Hardiman suggested that while there is no doubt
that an agreement in relation to the matter of a deposit is usual in contracts
for the sale of land, there was at least scope for the contention that deposits
may not be considered essential. The better view would seem to be that it is
not essential that a term in relation to the payment of a deposit must
invariably be included in order for there to be a concluded agreement and the
crucial question must be whether everything that there is evidence the parties
intended to include in the contract has been addressed.
Under section 51(1) of the Land and Conveyancing Reform act,
there must be a valid note or memorandum of the agreement. Only the material
terms need by included in a note or memorandum for it to be sufficient but all the terms, whether they be important
or unimportant must be agreed before there can be a concluded agreement. The note or memorandum must be in writing and
signed by the person to be charged or by someone authorised by him to do so. While what is material must depend on the
circumstances of the case, in Shirley
Engineering v Irish Telecommunications Investments it was stated that the
amount of the deposit was an essential term in the sense that it need be
included in the memorandum.
In Mulhall v Haren Justice
Keane stated that either read alone or with other documents which can be
properly read with it, the note or memorandum must contain a recognition,
express or implied of the existence of the oral contract to be enforced.
A further related issue which has caused considerable
controversy over the years is the effect of the inclusion of the words ‘subject
to contract’. Justice Keane stated that a letter which stated that a
transaction is ‘subject to contract’ cannot be a sufficient note or memorandum,
since the use of those words is normally inconsistent which a concluded
agreement. Only in very rare
circumstances, such as in Kelly v Park
Hall School could those words be dismissed.
However, in the Supermacs
Ireland case, Justice Hardiman stated that it was plainly arguable that the
use of the phrase ‘subject to contract’ did not preclude the existence of a
‘done deal’ between the parties. In the Jodifern
case Justice Barron suggested that if the words are contained within the
body of the document, it is a matter if construction of the writing as a whole
whther or not it is intended to deny the existence of a concluded agreement.
Thus an element of uncertainty has returned to this are of law.
Often where an oral agreement is reached between parties
there may be no sufficient note or memorandum and equity is faced with the
dilemma of insisting on strict compliance with formalities or allowing
alternative evidence of the agreement in order to prevent the perpetration of
fraud. A plaintiff may be able to obtain specific performance in the absence of
a note by invoking the doctrine of part performance, which allows a plaintiff
to rely on his own actions as evidence for the existence of an agreement.
In Lowry v Reid it
was stated that the issue is whther the plaintiff has an Equioty arising from
part performance which is so affixed upon the conscience of the defendant that
it would amount to a fraud on his part to take advantage of the fact that the
contract is not in writing. The right to relief rests not so much on the
contract as on what has been done in pursuance of it.
In Steadman v Steadman
it was suggested that it would be sufficient if the acts of part
performance in question were, on the balance of probabilities referable to some
contract and may be referred to the alleged one.
In Mackie v Wilde Justice Barron stated
that what is required is that acts relied upon as being acts of part
performance be such that on examination of the contract which has found to have
been concluded and to which they are alleged to refer, show an intention to
perform that contract. Ultimately the court seeks to ensure that a defendant is
not ‘breaking faith’ with a plaintiff by relying on a statute. What is
essential is that
1.
There was a a concluded oral agreement
2.
The plaintiff acted in such a way which showed
an intention to perform the contract
3.
The defendant induced such acts or stood by
while they were being performed
4.
It would be unconscionable and a breach of good
faith to allow the defendant to rely on the Act to prevent the performance of
the contract
The detriment to the plaintiff must be the result of what
the plaintiff does with the defendant standing by. These principles were
applied by Justice Laffoy in Liberty
Asset Management V Gannon
As Spry has stated, it should be emphasised that an act of
part performance must be judged not in the abstract but in light of all the
material circumstances in order to establish whether it is sufficiently
unequivocal. The acts upon which a
plaintiff seeks to rely in establishing part performance must be his own acts
and not those of the defendant.
A common example of part performance is the carrying out of
imporvements or alterations to the property. In Starling Securities v Woods it was held that entry onto land and the
demolotion of buildings thereon constituted part performance. Another common issue is the payment of
purchase money, which was traditionally not a sufficient act of part
performance. In Howlin v Thomas F. Power
Ltd. it was stated that while payment was a sufficient act, it was stressed
that the application of the doctrine was still confined to cases where it would
be fraudulent for a defendant to rely on the statute.
In England, the equitable doctrine of part performance no
longer exists.
A further issue that may arise in specific performance
actions relating to contracts for the sale of land is the circumstances in
which a party will be required to comply with a completion notice. A party
serving a completion notice must be ready willing and able to complete the sale
at the date of service of the notice. It is clear from the judgement of Justice
Barrington in Keating v Bank of Ireland that
a party cannot be forced by a court to close a sale before the issue of whether
he is entitled to compensation under the original contract has been confirmed.
As a general principle, the courts will not exercise its
discretion to award specific performance where damages would be more
appropriate. Therefore, as a rule specific performance will not be granted for
the sale of personal property. However, this is not a steadfast rule and
specific performance for the sale of personal property may be granted where the
item in question is of unusual beauty, rarity, or distinction. A further
question that has been suggested is whether or not the object in question is of
unique or peculiar value to the individual concerned.
In Falcke v Gray it
was stated that while you
cannot get specific performance for ordinary chattels, if the chattel is unique and damages wouldn’t
be an adequate remedy you can get specific performance – unless the object had
been sold to a 3rd person, then you get damages.
In Cohen v Roche the order for specific performance was refused
because it was ruled that there was an adequate remedy in breach of contract.
The issue of whether or not the items are freely available elsewhere is usually
the go-to test. This was seen in the
case of Sky Petroleum Ltd v VIP Petroleum
Ltd. This approach has been followed in relation to the sale of shares in
the case of Duncuft v Albrecht. This has been also
shownby the case of Pernod Ricard &
Comrie plc v FII Fyffes plc (1988) where the courts were called on to
resolve a dispute which arose following intense negotiations, regarding the
purchase of very valuable shares, conducted by a large number of persons over
three days. The courts had to examine the negotiations in detail and, on the
facts, held that an offer had been made by the defendant which had been
accepted by the plaintiff.
By their nature building contracts
will often be of an intricate and indefinite nature involving the performance
of a variety of different obligations. As stated in Rushbrooke v O’Sullivan the
attitude of the Courts towards their enforcement has not always be consistent
but the dominant view is that they should rarely be enforced. In practice, the
likelihood of obtaining specific performance hinges on two main issues;
primarily the certainty of the terms of the contract and to a lesser extent the
degree of supervision which an order would require.
The leading case on the matter is Wolverhampton Corporation v Emmons where
the three necessary conditions for and
order of specific performance to build or repair. First the work in question
must be defined in the contract, secondly the plaintiff must have a substantial
interest in the performance of the contract and damage must not be an
appropriate remedy and thirdly, the defendant must have by the contract
obtained possession of the land on which the work is contracted to be done.
In Redland bricks v Morris it was said that the Court must be careful
to see that the defendant knows exactly in fact what he has to do. It has been
stated that this requirement of sufficient definition does not mean that the
contract must be so specific that it leaves no doubt and Spry has suggested that the requirement
should be that the obligations in question must be at least so clear that it
will be possible for the court to determine whether the acts of the parties do
or do not amount to part performance.
Clearly where the defendant is in
possession of the lands specific performance may often be the preferred option
as the plaintiff could not employ another builder without committing a
trespass. The Courts will be more
willing to grant specific performance where supervision is not required. This
was the case in Co-op Insurance v Argyll
Stores.
As a general rule contracts which
involve the performance of personal services will not be specifically enforced.
This is due to a combination of the Courts dislike for supervision and their
unwillingness to compel individuals to work together. However, as was said in Lift Manufacturers v Irish Life Assurance this
is not a rigid ban.
These issues were examined in
detail in CH Giles & Co v Morris where
it was that just because an element of personal service was involved in the
contract did not automatically exclude it from specific performance. The matter is one of balance of advantage and
disadvantage in relation to the particular obligations in question.
There are strong policy
reservations against specific performance of employment contracts. However, in
exceptional cases such as Hill v Parsons
& Co Ltd the courts will enforce a contract. In De Francesco v Barnum a 14 year old girl
entered into a contract to learn stage dancing. Her contract of employment
prevented her from marrying and accepting other work. The court held that the
contract was not able to be specifically performed.
In Ryan v Mutual
Tontine Assoc a lease of a service
flat provided that the lessors should provide a porter who was to be
'constantly in attendance'. It was held that this undertaking could not be
specifically enforced. It would require 'that constant superintendence by the
court which the court has always in such cases declined to give'.
In Posner
v Scott-Lewis The court granted an
application for specific performance of a lessor's covenant to employ a
resident porter for certain duties. The court distinguished Ryan v Mutual
Tontine, where supervision of the execution of the undertaking had been
required. Here neither personal services, nor a continuous series of acts, were
required, but merely the execution of an agreement containing provisions for
such services.
In recent times, the ‘Keep Open’ clauses of contracts
between supermarkets and shopping centres have become a key area for specific
performance. In Co-operative Insurance
Society Ltd v Argyll Stores the Co-operative Insurance Society Ltd (CIS)
owned the freehold of a shopping centre and they let the anchor unit to Argyll
Stores as a supermarket, for 35 years from 1979, with a
covenant to ‘keep open the demised premises for retail trade’. In 1995, the
store was making a loss and Argyll closed, despite the protests of the Co-op.
The Co-op argued that they should be awarded specific performance, on the
ground that it was necessary to keep a store open in an otherwise depressed
area.
The trial judge refused a specific performance order. The
Court of Appeal granted specific performance by a majority, because there was
considerable difficulty proving a loss suffered and Argyll had acted with
‘unmitigated commercial cynicism’.
The House of Lords allowed Argyll Store’s appeal and said
the judge’s exercise of discretion was correct in refusing an award of specific
performance. Damages were the appropriate remedy. There were a number of
relevant considerations. First, it was settled practice that no order would
make someone run a business. Second, enormous losses would result from being
forced to run a trade. Third, framing the order would be unduly difficult.
Fourth, wasteful litigation over compliance could result. Fifth, it was oppressive
to have to run a business under threat of contempt of court. Sixth, it was
against the public interest to require a business to be run if compensation was
a plausible alternative.
Lord Hoffmann gave the leading judgment.
“
|
The purpose of the law of contract is not to punish
wrongdoing but to satisfy the expectations of the party entitled to
performance... The exercise of the discretion as to whether or not to grant
specific performance starts from the fact that the covenant has been broken.
Both landlord and tenant in this case are large sophisticated commercial
organisations and I have no doubt that both were perfectly aware that the
remedy for breach of the covenant was likely to be limited to an award of
damages. The interests of both were purely financial: there was no element of
personal breach of faith... No doubt there was an effect on the businesses of
other traders in the Centre, but Argyll had made no promises to them and it
is not suggested that CIS warranted to other tenants that Argyll would
remain. Their departure, with or without the consent of CIS, was a commercial
risk which the tenants were able to deploy in negotiations for the next rent
review.
|
There are various defence which
may be put forward when a claim for specific performance is made, the majority
of which are discretionary in nature.
Lack of Mutuality
It has been traditionally accepted
that a court would not grant specific performance at the suit of one party when
it could not do so at the suit of another and that in order to obtain a decree
of specific performance, the contract must be mutually enforceable.
In O’Regan v White it was stated that generally speaking, at any rate,
it would not be even handed justice to compel specific performance against one
party where the same remedy would not be available against the other in respect
of matter to be performed by him under the contract.
One question which has provoked
controversy is whether the question of mutuality is to be determined at the
time the contract was entered in to or at the time of judgement. In Price v Strange the Court of Appeal held
that the time at which the mutual availability of specifc performance must be
considered is the time of judgement and said that the correct principle is that
the Court will not compel a defendant to perform his obligation speciofically
of it cannot at the same time ensure that any unperformed obligations of the
plaintiff will be specifically performed.
Misrepresentation
The fact that a contract was
induced by reason of a misrepresentation will usually be a defence for an
action for specific performance. Any misrepresentation which justifies
rescission will suffice and specific performance may even be refused where
there is no right to rescind.
Misrepresentation will only
provide a defence to an action for specific performance where it has induced
the defendant to enter into the contract and he has been prejudiced as a result
although it may not be necessary to prove that the misrepresentation provided
the sole motivation for the defendants decision to enter into the agreement.
If the defendant has entered into
the material contract or has elected not to rescind in reliance on misleading
statements or actions of the plaintiff, specific performance is refused either
if circumstances of unfairness render it unreasonable to grant relief or if in
view of the error or misunderstanding of the defendant and the hardship that
may be suffered by him it is unreasonable to grant relief.
Mistake
In certain circumstances, mistake
will constitute a defence to an action for specific performance. In determining
whether specific performance should be refused on this ground the court will
often be primarily influenced by the unfairness or hardship caused by any
misapprehension on mistake or hardship caused by the mistake on the part of the
defendant.
The mistake may be of such
proportions that it prevents a valid contract coming in to existence at all; in
these circumstances clearly no order of specific performance can be made.
However, it is also necessary to consider the types of mistake which although
they do not prevent the contract from being made, may be of such a nature that
a Court will in the exercise of its discretion refuse to grant specific
performance.
There will also be types of
mistake which are neither serious enough to justify rescission nor to provide a
good defence in an action for specific performance. This can be seen in Ferguson v Merchant Banking.
Where a defendant seeks to rely on
mistake as a defence often a crucial question will be whether the plaintiff
contributed in any way to the misunderstanding. In Tamplin v James the mistake was purely the defendants fault and so
specific performance was granted. This
was adopted in O’Neill v Ryan in this
jurisdiction.
In Stewart v Kennedy it was stated that while a court may refuse
specific performance in cases of mistake not caused or contributed to by the
plaintiff it has acted in this manner because it would be unreasonable to
compel the defendant to carry out his obligation.
Hardship
A Court may refuse to order
specific performance where to do so would inflict unnecessary hardship on the
defendant even where the plaintiff is not responsible for this. This was seen in Lavan v Walsh.
While most cases require the
hardship to have existed at the time of the contract, in exceptional cases,
supervening hardship may be relied upon, as was seen ion Patel v Ali.
Impossibility and Frustration
A Court will not make an order of
specifc performance compelling a party to a contract to perfrom his obligation
where it will not be possible for him to comply with the order which the court
proposes to make.
National Carriers Ltd v Panalpina (Northern) Ltd [
“Frustration of a contract takes place when there supervenes an event (without
default of either party and for which the contract makes no sufficient
provision) which so significantly changes the nature (not merely the expense or
onerousness) of the outstanding contractual rights and/or obligations from what
the parties could reasonably have contemplated at the time of its execution
that it would be unjust to hold them to the literal sense of its stipulations
in the new circumstances; in such case the law declares both parties to be
discharged from further performance
No comments:
Post a Comment